From Kevin Simpson, RFT, MEM |Environmental, First Nations and Regulatory ManagerWastewater Treatment Project, Capital Regional District:
The CRD has just received a Tree Cutting Permit from the District of Saanich authorizing tree removals at our site in Haro Woods.
[…] The footprint has been made slightly smaller, as Saanich staff wanted to maintain a visual buffer along Arbutus Road.
I anticipate that you could see workers on site next week, surveying and making plans. It’s likely that fencing and signage will go up towards the end of next week. Clearing will likely start the week of the 25th, but could start at the end of next week.
A construction notice will be sent in the coming days by CRD to neighbours.
For further information, contact:
Kevin Simpson, RFT, MEM
Environmental, First Nations and Regulatory Manager
Wastewater Treatment Project, Capital Regional District