From Shane Gilbert, Project Manager/Estimator at Copcan Civil Ltd. advises:
Good Afternoon,
As construction continues short durations of road closures will be required. The closure dates and durations are detailed below:
- August 15th, 16 and 19–23: Finnerty Rd between Edgelow St and Arbutus Rd will closed and only open to local traffic and emergency vehicles.
- August 26–30: Finnerty Rd between McKenzie Ave and Edgelow St will be closed, and only open to local traffic and emergency vehicles.
These closures will be in effect from 7:00am to 6:00pm, Monday to Friday, and normal traffic pattern will resume by 6:00pm.
There will be work on Saturday August 16 between 7:00am–4:00pm, with single lane alternating traffic through the construction site. Normal traffic pattern will resume by 4:00pm.
If you foresee any issues or would like more information please feel free to give me a call at (250) 754-7260, or reply to this email.
Thank you for your continued patience throughout this project,
Shane Gilbert | Project Manager/Estimator
Copcan Civil Ltd.