Andrew Giles, Parks Construction and Maintenance Manager at the Parks and Recreation Department of the District of Saanich, reports: 

Just wanted to share an update on the Cadboro-Gyro Park project.

Drainage work is complete and the pump is online. Operational adjustments to the pump will be made over the next few rain events to determine optimal settings. The parking lot is nearing completion, and will be formally open for public use after Friday December 11. Park areas impacted by construction will be restored in the spring.

The lot will also be temporarily opened for the Royal Victoria Yacht Club’s Christmas Sea of Lights boat parade on the evening of Friday December 4 (sail past at 7:30pm).

For more information see www.saanich.ca/parkrec/parks/projects/current/cadboro.html.